19 Oct 2006 12:00 AM by krisb Star rating in Preston, Lancs. 55 forum posts Send private message

Hi, Just wondering in anybody else has benn informed of the delay.  I rec'd an email today from keymare saying phase 2 would be ready sept 07 when we were originally told May 07. Anybody else heard this. Thanks, Kris 


Like 0

Spam post or Abuse? Please let us know

20 Oct 2006 12:49 PM by the2wyatts Star rating in Hornchurch. 5 forum posts Send private message

Hi,

We are buying on phase 2 and have not heard anything from key mare (I dont think that they have my email address.) As this is a long delay I would think that we should get a letter, our contract states 30/3/06. Do you have a date on your contract? I did ask this same question on VIVA ALMERIA but no one else sais that they had a date on their contract. Did Key mares email give any further information?



Like 0

Spam post or Abuse? Please let us know

23 Oct 2006 9:55 AM by DMBRIDGE Star rating. 102 forum posts Send private message

Hi all,

We are also buying in Phase 2, but have not been notified of any delay and cannot see a date on the contract itself though there is no doubt other paperwork said May completion. In fact we were told by KeyMare that the actual building work would be completed before May but they could not cope with all the Phase 1 & 2 Contracts at once andtherefore they would be staged through from March to May.  

We will be visiting Vera in the middle of November and intend visiting Key Mare to discuss the situation.  I will also ask my Agent to investigate and will report back any news.

Best Regards

David



Like 0

Spam post or Abuse? Please let us know

23 Oct 2006 9:58 AM by stubecc Star rating. 30 forum posts Send private message

Hi, your comments have shocked me, i have bought on phase 1,  i am repeatedly being told that they are still on March/April completion date, has anyone actually been given written confirmation of this delay or is it just a rumour.

 



Like 0

Spam post or Abuse? Please let us know

23 Oct 2006 10:01 AM by stubecc Star rating. 30 forum posts Send private message

Thanks for that info David. You have got my permission to kick ass in November if there is a delay that long!!!


Like 0

Spam post or Abuse? Please let us know

23 Oct 2006 10:03 AM by krisb Star rating in Preston, Lancs. 55 forum posts Send private message

Hi All,

I rec'd the email in response to me asking for confirmation from the builder as to an exact completion date as i wanted to book flights etc.  I was hoping to get out in may half term with my kids but looks like i won't even get out in Aug Summer hols.  I asked the builder if i could delay my last payment to coincide with the delay but they stated there was no delay.

This is the transcript of the exact emails i have received.

"With regard to your request we received through our website, please be informed that the completion for Thalassa II is scheduled for the end of august/ beginning of september 2007. We cannot make it before March 2007.
 
Kind regards,
Ursula Horck
Client Care Department"
 
 
"Regarding the next payment, I inform you herewith that the signed contract should be fulfilled. So, it can not be postphoned. Besides, there does not exist a delay in the completion of Thalassa II.
 
Kind regards,
Ursula Horck"
 
Cheers all, Kris
 


Like 0

Spam post or Abuse? Please let us know

23 Oct 2006 10:20 AM by stubecc Star rating. 30 forum posts Send private message

How can they say there is not a delay, when they have told you September, the completion date has always been March/April.

As regards to your final payment this does not have to be paid until final completion.

I cant understand where this 6 month delay has come from all of a sudden.

My purchase contract clearly states that completion is 24 months from April 05, and that compensation kicks in 3 months after this.

Regards Stuart.

 



Like 0

Spam post or Abuse? Please let us know

27 Oct 2006 5:09 PM by jeffw Star rating. 18 forum posts Send private message

For general information- we have had a confirmation e mail direct from key mare stating phase 1 will be complete May 2007, this ties in with what the development office were advising on our last visit earlier this month.


Like 0

Spam post or Abuse? Please let us know

28 Oct 2006 2:55 PM by stubecc Star rating. 30 forum posts Send private message

  For Info,

 I have just had it confirmed from my solicitor that there is a delay, she said at the moment they could not say how long, but could be "June, July etc" to quote her e-mail. She said she would et us know as soon as she had more details.

Regards.



Like 0

Spam post or Abuse? Please let us know

29 Oct 2006 10:02 PM by downsfennon Star rating. 252 forum posts Send private message

I have after seeing this sent my agents and solictor as message as we are going over in January to do our paperwork will inform message board

 

 



Like 0

Spam post or Abuse? Please let us know

30 Oct 2006 5:10 PM by downsfennon Star rating. 252 forum posts Send private message

have sent 4 emails and rang the agents twice today with no reply re this date

just the general letter of confirmation that it is march-april?

very frustrating

 

 

 



Like 0

Spam post or Abuse? Please let us know

30 Oct 2006 5:15 PM by downsfennon Star rating. 252 forum posts Send private message

have rec 2 e mails

 

1 ready for march -april and the same agents april -may



Like 0

Spam post or Abuse? Please let us know

31 Oct 2006 1:44 PM by stubecc Star rating. 30 forum posts Send private message

Just had an e-mail back from Key Mare Customer Care saying that completion for Phase 1 is in May 2007.

This sounds better news than some of the rumours.

Regards.



Like 0

Spam post or Abuse? Please let us know

31 Oct 2006 6:43 PM by downsfennon Star rating. 252 forum posts Send private message

My solicitor knows of a delay but not the month

My agents for phase 2 are saying july , and i have been told march april may? in the same week



Like 0

Spam post or Abuse? Please let us know

01 Nov 2006 6:50 PM by downsfennon Star rating. 252 forum posts Send private message

may i ask what phase everyone is on


Like 0

Spam post or Abuse? Please let us know

02 Nov 2006 7:40 AM by DMBRIDGE Star rating. 102 forum posts Send private message

I am Phase II.  We were originally told by a Key Mare representative that there was very little difference in the actual building completion date for Phase I & Phase II. The reason for having 2 phases was because of the number of properties involved and the length of time it will take to complete all the paperwork involved for final completion.

I have emailled Key Mare, but no response.  I will confront them in a couple of weeks when I visit Vera.

Brgds

David

 



Like 0

Spam post or Abuse? Please let us know

02 Nov 2006 8:41 AM by hterag Star rating. 100 forum posts Send private message

 

We're buying on Fase A and I've just had a reply from Key Mare to say that it's scheduled to complete May 2007. I've pasted it below.

Buenos días,
 
The Thalassa phase A is scheduled to be completed in May 2007.
 
Kind regards,
Ursula Horck


Like 0

Spam post or Abuse? Please let us know

02 Nov 2006 10:42 AM by jeffw Star rating. 18 forum posts Send private message

we are on phase 1 and have had the same mail from key mare as hterag!


Like 0

Spam post or Abuse? Please let us know

02 Nov 2006 11:45 AM by krisb Star rating in Preston, Lancs. 55 forum posts Send private message

the email i pasted earlier is regarding phase 2.

Thanks, Kris

 



Like 0

Spam post or Abuse? Please let us know

03 Nov 2006 9:46 AM by the2wyatts Star rating in Hornchurch. 5 forum posts Send private message

Hi All,

Just got this reply from query sent to Key Mare Sunday:

Dear Mr and Mrs .....
 
Regarding to your apartment at Al Andalus Thalassa we can tell that the completion will be at the end of Agust, beginning September.
We will contact you to give you information about bank details and will contact you to do a house viewing before completion.
 
With Kind Regards,
Petra
 
 
 


Like 0

Spam post or Abuse? Please let us know

Pages: 1 | 2 | Next |
Post reply   Start new thread


Previous Threads

buying as a private person or with "sl" - 0 posts

30 posts were found:


1 | 2 |
Our Weekly Email Digest
Name:
Email:


This site uses cookies. By continuing to browse you are agreeing to our use of cookies. More information here. x