Steve here buying in block 8. I was holidaying in benalmadena last week and popped down to duquesa last monday 4th. My first visit in two years!!. Major progress!!!
I have posted four photos. One is of the road running below block 8 and the other three and in and around the development to show people how well it looks.
I was very impressed with the development and things have moved on. I visited my solicitor in sabbi on monday before I went to the development. The developer told him that they will progress getting the habitation licence for the remainder of phase 1 end aug / early september.
Here's my observations from last monday:
1. The place looks fantastic. I haven't seen a better development and the location is excellent...I've been stuck up in the hills around benalmedena without a car for 9 days!...getting food and travelling has been a real pain in the bum...in duquesa everything is 5 minutes walk....it makes a real difference.
2. The road photo I posted doesn't show it has moved on much from earlier photos...there was no one working on the roads and a just a handful of plasterers were clocking off from phase 2 and pahse 3 (maybe 4) couldn't tell.
3. There was no construction activity on the other phases that I could see.
4. The developer obviously needs to finish the roads before any chance of the license. That is going to take alot of effort from a big squad of guys to complete by the end of the month...I don't see it happening. I wonder whether August is a go slow month in the building trade because of the heat / spanish holdays?
5. I pushed my completion expectation out to easter next year!!!. We'll have to wait and see.
Congratulations for everybody who has completed and enjoy.