24 Jun 2009 1:27 PM:
All,
We received this yesterday from Polaris world owners club
TERRAZAS DE LA TORRE PHASE 2
(Blocks 267-276 & Blocks 285-290)
At a meeting with Polaris on 17 June 2009 they confirmed the following:-
Blocks 285-290
Construction has started. A completion date was not given but we expect that they will be ready to be handed over during the first quarter of 2011.
Blocks 267-276
Construction has not yet started. It is anticipated that building work will commence shortly after the summer break i.e. September/October 2009. A completion date was not given but, if work does start as indicated, this would suggest a handover around the middle of 2011.
They said that the golf course will be ready for playing before 31 March 2010. The Club House is being moved to a location close to the Town Centre.
There is no date for the construction of the Town Centre. In the interim a small supermarket will be available near the Clubhouse.
Not sure if this ties in with anything people have seen or been told
Sa
Community thread:
PHASE 2 - STARTED AT LAST
--------------------------------------