05 Oct 2008 10:30 AM:
We signed up in September 06 and were told completion would be May 2008. We too are devastated. From lawyers we get the impression that succeeding with an application for the contract to be rescinded depends not only on the time delay but also the reasons for the delay. We are informed that Roda made late changes to the plans, which then took time to approve, but we do not know if this is a sufficient reason. We meet our lawyer soon and will ask more questions. We shall seek to rescind if our property has been moved at all in the new plans and the view or the relationship to the sun is different from when we contracted.