11 May 2007 2:07 PM:
Hi Al-Lin,
I agree in part to your idea of using the fees to finish some of the areas, even though it annoys me to let Jale of the hook, which is probably what they are waiting for, but, there are some serious cracks (please see latest photos) which i feel Jale must put right first on the walls as they will only cover them in cement and we are then back to square 1.
Yes, i know jale have no plans to carry out this work, thats why i have previously suggested to withold 5% back upon completion and a stipulation that Jale have say £ months to complete outstanding works( lets say till the end of July ish) if not done by then the 5% withheld monies can then be spent on these works. Fairl common practice in UK and Fairly common for the builder to not finish thus losing the money.
Least then its their money not ours. Occupied premises if in agreement could then pay a percentage.
What do you think?