19 Jun 2009 2:26 AM:
Hello
I just wanted to let you know that I had serious concerns about this development last summer what with the change of the economy. I too signed contracts in December 2006 paid deposits and received (Thankfully) BG's (after much chasing). SO in september last year I thought there must be a way out of this contract legally - I noticed the get out clause that said you could formally rescind the contract within something like 14 days of the 18 months months following the building licence being approved if the developer is not in a position to complete or the hacitacion licence is not in place. Then the following clause says the developer is not responsible for delays beyond their control which basically looked like even if you did try to rescind they would say the delay was out of their control and that was why they could not complete. Therefore making it impossible to end the agreement which posed the question of whether the contracts were legally acceptable and (as I had used a lawyer for the purchase) if they were not then surely I'd have a case against my lawyer for negligence as they should have seen that the contract was unfair. As it turned out my lawyer (AT THE TIME) said he tried to change the 'force majeur' clause but Cley Ges refused - he then said that as I had a guarantee I didn't have to worry because if it was NEVER finished I could get my deposits back under the guarantees.
So I looked at the documents I had and saw that the building licence was approved in March 2007 and that the 18 months and 14 days would end in 48 hours - so I tried to get my then solicitor to rescind the contract but they weren't available! - so I did it myself by way of letter to Cley Ges in english then used google translate to turn it into Spanish. My then solicitor said I shouldn't have done that and that it wasn't acceptable so I 'told him' to do it for me as my lawyer - he said he quit!! So I had to find another lawyer with 24 hours to go to put the rescind request in formally - it had to be sent by Burofax - i didn't know what that was! Luckily on this site I believe I found Roberto Leiro of Lawyers of Spain in Marbella - he has been absolutely invaluable. So he read emails between me and my former lawyers about the whole Las Hig scenario he got the formal request to rescind in time and as they did that they requested a refund of monies paid under the BG's from CAM due to the failure to complete in time - CG said its not their fault why its delayed and CAM ignored the request. That was in September last year. Roberto told me that in Spain things take long and the courts usually give a developer a further 6 months after the contracted completion date to complete and that there was really no point trying to take it to court just yet. He said I had 4 options - 1. To complete the purchase when ever it happened (as an invester this was not an option for me) 2. Wait another 6 months then request the money back from CAM 3. Go to court now and try to sue the developer and Cam bank 4. Sue my previous lawyer for negligence if I can't rescind or get my money back from the guarantees.
Knowing I had been exploited by my previous lawyer I was refreshed to hear straight talk for once. He said the best and most cost effective thing for me to do was to wait the 6 months as it looked like the development wouldn't complete before then but I had to do it before the certificate de habitacion was issued. In January of this year I had a letter from the developer through Spain Select the agents saying I had to arrange to come to spain to sign the contract as the certificates were due to be issued. I did not go I waited - Roberto called CAM again requesting a refund under the BG's but they ignored him. He said we should ask one last time in March when it'll be 6 months overdue if we get no joy then we'd have to consider legal action against the developer and CAM which would cost money.
So I was about to email Roberto 2 weeks ago to find out if it was now time to go to court when I got an email from him instead saying CAM have contacted him asking for a copy of proof of payment of the deposits - I got them off to him that day via email. Then a few days later CAM called him back to say they need the original guarantees in order to refund the monies I paid - so I got them off. On Wednesday of this week Roberto Leiro of Lawyers of Spain emailed me to say he's given the bank guarantees in and had got a cheque for all of the deposit paid plus legal interest and that as soon as the cheque cleared he'd deposit the funds into my account! I CAN NOT BELIEVE IT - I won't believe it until I see the money in my account - the pessimist in me thinks they'll cancel the cheque! So I won't say I've won just yet but if and when my bank account looks a lot healthier I shall let you know.
Good luck - I feel for everyone on this development - it would have been and may well still be a wonderful development - if you 'don't need the cash' right now if the development does finish it'll be a brilliant investment however the emphasis is on IF!!
Email roberto @ lawyersofspain. com to see if he can help you out tell him Miss A McG recommended him. Only because he's aware of the situation of the development and the unfair contracts issued and he seems fair - not just out for money!!!
GOOD LUCK
This message was last edited by adaurable1 on 19/06/2009.
This message was last edited by adaurable1 on 19/06/2009.
Community thread:
Return of deposits for latter phases
--------------------------------------