18 Mar 2008 9:57 AM:
Hi, i have brought one of the apartments in this development, and have just returned from a site vist, there is no way in a million years the first phase will be ready at the end of April like i am being told. I would estimate "being a builder myself" that they have atleast 4-5 months of work before phase 1 is even compleated, not alone phase 2 and 3. The finishing is terrible and the walls of the apartments have been finished in artexing which looks cheap. kitchens have been fitted and to be fair look very nice. Apartments are a lot smaller than i had been lead to believe and i have a great view of the block infront of me instead of the sea, which again i had been sold on.
Wolud be very interested in your thoughts on the matter.