Sometimes they do ask for the list within 15 or 21 days - I think thats so they get it done s a job lot. You will have a 'builders' guarantee which should last but you will have to enforce it from the experiences I know of
As Justin says, she who shouts loudest gets snags done first!!!!!!!
_______________________
Quite frankly m'dear, I don't give a damn!
www.herbalmarbella.com
Spam post? Please let us know
|
|
From my own experience it seems that some developers read the forums on this site and get quite agitated by the comments. This goes some way to rattling their cages into action (or not!).
Spam post? Please let us know
|
|
|
|
|
|
|
Hi All.
is the time limit for snagging before or after the deeds signed?
cheers
_______________________ Despreocupado
Spam post? Please let us know
|
Maria,
Can my lawyer legally delay the signing of the deeds until all snagging and terms of the contract are completed?
Cheers,
Ken.
Spam post? Please let us know
|
Emphatically yes he can postpone the signing when any term of the contract is not completed.
Snagging... depends on the kind of snagging. There is no law stablishing what kind of snagging needs to be repaired before completion and what of them after. I would say the before completion the house needs to be in perfect conditions of habitability in every one of its elements and if not, you are not obligued to complete.
The clue is that developers have been having the upper hand for years and are used to subdue bad informed consumers. That needs to change and consumers need to have the last say. That is what contract and consumers Law in Spain deffend,a different situation is an abuse.
Do not allow yourself to be put off... of course, with the help fo a good independent advisor with Consumers Law Expertise.
This message was last edited by mariadecastro on 5/17/2008.
_______________________
Maria L. de Castro, JD, MA
Lawyer
Director www.costaluzlawyers.es